Current Progress

Level 3 concrete structure:          100%

North existing ramp:

Existing toppings removed,  waterproofing membrane currently being installed.  (60%)
Heating lines:                     35%
Concrete topping:           20%

Exterior wall construction
Frame and Board :           90% complete
4 stair towers:                   95% complete
Stucco Buildouts:             75% complete (Frame, board, flashing)

Level 2 waterproofing / concrete toppings:  45% complete

North Mechanical Room:
Walls framed and boarded:  100%
Roof:   100% complete

Wall torch-on:  100%  complete
Starting insulation and cladding

Central Atrium:
Curtain wall currently under construction:  30% complete

Roof:  100% complete


Food Court:
Mechanical / Electrical rough-ins:  Complete

Wall framing:  Started

Ceiling layout:  Complete (started frame in)


Interior Mechanical / Electrical work:      On-going


East Parkade:    
   North Stair:         Elevator Pit Walls:  Complete
                              Grade Beams and Slab on Grade:  Complete

                              Precast support columns:  Complete

                              Precast removal:   Complete

Shaft walls forming:  Started

South Stair:        
   Excavation:  Completed

   Elevator pit wall, Grade Beams, Slab on Grade:  Complete

   Precast Support Columns:  Complete

   Precast removed:  Started

Last Tower Crane Removed March 12-14.

Project Description

Over the past 36 years, Southgate Centre has been a part of the South Edmonton community.  The new construction will add 155,000 square feet on the ground level.  There will be two levels of parking directly above the expansion serviced by escalators and elevators descending into the grand atrium area.

Inside Southgate Centre, the west side feature court floor is being upgraded with new terrazzo patterns.  The marble tile with unique floor patterns will be carried into the expansion.  The lighting levels that are currently in the existing Centre will be carried throughout the new construction.  Finishing the common areas throughout the entire Centre will be completed with modern and relaxing colours and furniture. 

The west exterior will incorporate the existing brick with metal cladding and glazing to give the Centre an urban appeal to develop an interesting and attractive streetscape as well as screen the parkade.

 

 